Tuesday, June 5, 2012

Towson Reservoir Construction Plan


Community Update

May 31, 2012


Scope of Work:

Construction of a new storm drain system in Far Hills Drive and Hillen Road.
Demolition of the existing Towson Reservoir and construction of a new Covered Finished Reservoir; work to be completed in 2 Phases:
1.      Demolition and construction of the Covered West Basin and associated work.
2.      Demolition and construction of the Covered East Basin and associated work.
Replacement of the pump station electrical motor control center and pump valves and vaults.
Site Security and Instrumentation improvements.
Replacement of a section of the 36” water influent main and valves along the west curb lane of Stevenson Lane.
Landscaping improvements; removal of dead & dying trees.
             

Contact Personnel:


Baltimore City Construction Project Supervisor
            Mr. Avon Holland: 410-396-3671
Baltimore City Engineering Supervisor
            Mrs. Larisa Feldsher: 410-396-7300
Baltimore County Engineer:
            Mr. Gerald McHenry: 410-887-3784
Design Engineer: Gannett Fleming, Inc.
Contractor: Whiting-Turner Contracting Company

Project Status:  May 31, 2012

Contract Amount                      $18,393,000.00
Notice to Proceed                    7-12-2010
Construction Time                    1155 Calendar Days
Contract Completion Date        9-9-2013
Percent Contract Completed     64 %
Schedule Status                        On Schedule

Progress to Date:

The Construction Schedule has been approved and is updated monthly. In addition, the team has reviewed and processed approximately 260 submittals for approval of equipment and materials to be used for this project. The construction team holds monthly Progress Meetings to evaluate construction progress.

Utility Work:

The first construction work, in accordance with the planned sequence of construction, is the construction of the new storm drain, inlets and manholes in Hillen Road and Far Hills Drive. This work is necessary to provide a larger storm drainage system for the Reservoir property. This work is complete.

A new permanent water service to 1210 Stevenson Lane has been constructed under a separate contract. This work stems from the unique location of the original water service to that historic residence and its relation to construction activities for this project.

West Basin Work Completed:

A steel, sheet-pile wall has been installed to protect the East Basin, and will remain in operation during the Phase 1 demolition and construction of the new West Basin.
‘Punch List’ repairs are in progress at the West Basin.
Water-tightness testing of the completed West Basin structure is on-going; the contractor is repairing wall leaks.
Application of the roof vapor barrier is proceeding and re-coating is scheduled for next week.. Following approval of this testing, construction of the remainder of the roof system will continue.

Other Phase I Work:

New Reservoir piping and valves are being installed. Testing of these pipe systems will continue to be scheduled as completed.
Construction of the new electrical Motor Control Center is in progress; Phase II of this electrical work (Bus B) has been completed and approved.
Construction of new electrical and instrumentation ductbanks is in progress; the contractor is currently pulling cables in these conduits.
New permanent paving was completed at Stevenson Lane.

Upcoming Work Schedule:

The contractor is continuing work operations for Phase 1 of the project.
Sediment and erosion controls are in place and maintained as necessary.

Hydrostatic testing of completed pipe work is pending repairs to piping in the Effluent Chlorination/Meter Vault.
Construction of new electrical and instrumentation ductbanks and vaults is underway throughout the project site. The contractor is installing power and control cables.
Remedial work for the new West Basin roof membrane coating is proceeding.
Phase II testing of the new Motor Control Center for the Towson Reservoir is complete.
Installation of new Chlorination Pipework is underway.


Community Concerns:

1. Concern:
The contractor stated they received an unconfirmed complaint from a resident of Far Hills Drive concerning vibration to their residence during demolition. There have not been any further complaints.
 Action:
The contractor hired a specialty firm to monitor vibration during the installation of the sheet-pile protection wall. The reports indicate that the work did not exceed unsafe limits. The contractor and inspection team will continue to monitor work operations for any excessive vibration. This phase of work is complete.

2. Concern:
The County received a complaint regarding excessive mud and stone on the adjacent roadways on January 19, 2011.
Action:
The contractor was directed to clean the roadways immediately and to establish a schedule for inspection and cleaning of the roadways on a regular basis. The roadways have been satisfactory since that incident. The contractor is maintaining daily clean-up of the streets. No further complaints have been received.

3. Concern:
The existing water service to 1210 Stevenson Lane runs through the Towson Reservoir property and interferes with the planned construction of the new West Basin.
Action:
The City approved construction of a new temporary water service to be constructed away from the location of the new basin facilities; this work was expedited, after approval, and has been completed. A new, permanent water service from Stevenson Lane is under design and will be constructed under this project.

4. Concern:
Several neighbors on Garden Road have complained, through Councilman Marks’ office, that there is excessive noise from waiting dump trucks, prior to the required 7:00 AM start time for construction activities.

Action:
The contractor has notified their subcontractor about the restriction to begin any construction activity prior to 7:00 AM each day. The contractor has also been advised to modify the truck scheduling plan to avoid having waiting trucks on residential streets. The inspection staff will also monitor this situation and take appropriate action if further violations are witnessed. No new complaints received.




5. Concern:
11-16-11: Residents filed complaints about the contractor working past the agreed upon 11:00 PM curfew deadline at Stevenson Lane, during construction of the new Influent Manifold.

Action:
The contractor was inadvertently given permission by the onsite inspector to complete a work phase that night. All contract parties were subsequently told that no violations of the 11:00 PM deadline would be allowed under any circumstances. This included written notification to the contractor. There were no further infractions of the curfew deadline by the contractor.

6. Concern:
Baltimore City reports that a motorist has filed a claim for tire damage due to construction activities on Stevenson Lane.

Action:
It has been recommended that the complaint for damage be transmitted to the contractor for investigation and action by their office and/or insurance company. We will follow-up and coordinate with contract parties.

7. Concern:
Baltimore County received an unconfirmed report from a resident on Dogwood Lane asking if recent issues with her water service could have been related to the influent manifold work performed by the contractor in Stevenson Lane.

Action:
The Baltimore City Construction Management team will monitor the situation and respond to any further complaints. To date, no other complaints regarding water service interruptions or water quality have been received from residents in that neighborhood.

8. Concern:
An inquiry was received as to when final paving would be completed on the perimeter roads due to the utility work completed.

Action:
The County was informed that permanent paving on Stevenson Lane has been completed. Areas of Hillen Road and Far Hills Road which were disturbed have been temporarily paved. Permanent paving will be completed following work activities requiring heavy truck traffic on those roads. All temporary paving is monitored and repaired as necessary.


None – June 2011
None – July 2011
None - August 2011
None – September 2011
None – October 2011
None – December 2011
None – March 2012
None – April 2012

No comments:

Post a Comment

All comments are welcome! Please keep it clean and on topic. Posts with offensive language and personal attacks will be removed.